2.
Approval of Minutes for March 26, 2013
3.
Resolution 13-61-R Awarding Contract for Wastewater Treatment Facility Improvements to Manusos General Contracting Inc. for an amount not-to-exceed $838,768.00 (Byron Ritchason 4/12/13)
4.
Resolution 13-62-R Awarding Contract for Diffuser Membrane Replacement to Hayes Mechanical for an amount not-to-exceed $60,733.14 (Byron Ritchason 4/12/13)
5.
Resolution 13-60-R Authorizing Certain Elected Officials and Staff to Receive Confidential Information Related to Prairie State (Gary Holm 4/12/13)
6.
Resolution 13-59-R Authorizing Task Order #5 with HBK Engineering for American Can Substation Demolition and Restoration Engineering Services for an amount not-to-exceed $27,320.00 (Steve Allen 4/11/13)