Posted on: June 9, 2023
Week of 6/5 – 6/9/2023
Lead Water Services continue to be successfully replaced on the SW side of the City. The contractor has been doing a great job at keeping the sites clean and stakeholders happy. By the end of the today, 6/9/2023, 59 lead services will have been replaced w...
Read on...
LSLR Project Updates
Posted on: May 30, 2023
City crews are beginning the fifth week of the lead service line project, and work is moving faster than expected. As of the end of last week, over 35 new service line replacements were completed.
Stakeholders will receive an email from the City advising of an impending call from Brandt Excavating requesting an onsite homeowner meeting. These emails are sent out typically one to two weeks prior to the meeting request.
Engineer’s ...
Read on...
Additional Info...
LSLR Project Updates
Posted on: May 8, 2023
Lead and Galvanized Water Service Replacement Project is underway and crews started on south Water Street.
Crews will be working on replacements at Water Street from Main Street to the dead end, Elm Street from south Batavia Avenue to south Water Street, and Union Avenue from south Batavia Avenue to south Water Street. From there, crews will be movin...
Read on...
Additional Info...
LSLR Project Updates